The Supervisor’s Question After the Outage
Third-party technology risk supervision and software vendor failure in Indian BFSI
Third-party technology risk supervision examines whether regulated entities can continue critical services when a technology supplier fails. In Indian financial services, a limited number of licensors supply core banking, loan management and payments software to many smaller institutions. For a supervisor, the failure of one such licensor is a sector-level event rather than an entity-level one.
Why is vendor failure a supervisory concern?
Vendor failure becomes a supervisory concern when many institutions share the same supplier. Smaller entities, such as cooperative banks and mid-sized NBFCs, typically have the least in-house engineering capacity to absorb a licensor’s collapse. If several of them needed to migrate at once, demand on alternative suppliers and implementation partners could exceed available capacity.
What do current directions already require?
The baseline already exists. Paragraph 12(f) of the RBI Master Direction on IT Governance, Risk, Controls and Assurance Practices (7 November 2023) requires source code or an escrow arrangement for critical applications. The RBI Master Direction on Outsourcing of IT Services (10 April 2023) requires exit strategies and continuity arrangements for outsourced IT. The open question is how preparedness is evidenced, not whether it is required.
Which questions reveal real preparedness?
The difference between a compliant file and a usable arrangement shows in the answers to four questions:
Supervisory question | Weak answer | Strong answer |
Which critical applications depend on which licensors? | A contract list | A criticality-ranked inventory by licensor |
Could the entity run the application if the licensor failed? | “Escrow is in place” | A verification report and a tested drill |
How long would recovery take? | Not estimated | Measured against the recovery time objective |
Who would maintain the released code? | Unknown | A named, pre-qualified partner |
What should a CIO do when the licensor is admitted to CIRP?
A prepared licensee acts in the first week:
- Notify the escrow agent and legal counsel.
- Engage the resolution professional, whose interest in preserving value usually favours continued support.
- Confirm that the deposit is current and recently verified.
- Activate the plan for a maintenance partner, in case release follows.
Quick answers
Does admission to CIRP itself trigger release? Only if the escrow agreement says so, and even then the moratorium question arises.
Is continued support likely? Often, for a period, because the licensee’s contract is part of the value being preserved.